Further to the notice, published on 20 May 2026, regarding the signing of the Joint Statement on increasing the capacity of the gas transmission interconnection between Slovenia and Croatia, we would like to inform you that the construction and trial commissioning of the Zabok–Lučko gas pipeline section have created the technical conditions for increasing the interruptible transmission capacity at the IP Rogatec interconnection point.
The increased interruptible capacity at IP Rogatec, in amount of approximately 800 MWh/h, can be booked, in accordance with the provisions of the CAM NC Regulation, at regular auctions of interruptible capacities on the PRISMA platform.
Upon completion of the trial commissioning of the above-mentioned pipeline section on the side of the neighbouring transmission system operator, Plinacro d.o.o., the entire increased capacity will be made available as firm capacity. All additional information will be published in due time.