Plinovodi d.o.o. has conducted a non-binding market demand survey on incremental capacity for interconnection points among Network Users between 06th April 2017 and 01st June 2017 according to the Articles 26-29 of the Commission Regulation (EU) 2017/459. Plinovodi d.o.o. together with adjacent TSOs publishes demand assessment report for interconnection points Murfeld/Ceršak, Gorizia/Šempeter, Rogatec and Tornyiszentmiklós/Pince.
Consultation:
Based on the demand assessment report for incremental capacity between Austria and Slovenia, the planned incremental capacity project is being consulted between 19.10.2017 and 19.11.2017. The Users can submit their possible comments to the mailbox skr@plinovodi.si.
- Consultation document for interconnection point Murfeld/Ceršak
Based on the demand assessment report for incremental capacity between Croatia and Slovenia, the planned incremental capacity project is being consulted between 29.11.2017 and 29.12.2017. The Users can submit their possible comments to the mailbox skr@plinovodi.si.
- Consultation document for interconnection point Rogatec
Plinovodi d.o.o. has conducted a non-binding market demand survey on incremental capacity of the Hungarian-Slovenian bidirectional gas flow. In cooperation and together with adjacent TSO FGSZ the Demand Assessments Report, according to the Articles 26 to 28 of Commission Regulation (EU) 2017/459, for interconnection point Tornyiszentmiklós/Pince was agreed and published.
Plinovodi d.o.o. has conducted a non-binding market demand survey on incremental capacity for interconnection points among Network Users between 2nd July 2019 and 27th August 2019 according to the Articles 26-29 of the Commission Regulation (EU) 2017/459. Plinovodi d.o.o. together with adjacent TSOs publishes demand assessment report for interconnection points Murfeld/Ceršak, Gorizia/Šempeter, Rogatec and Tornyiszentmiklós/Pince.
We would like to inform all interested stakeholders that, having preliminary consulted both the Hungarian and the Slovenian regulatory authority, Plinovodi d.o.o. and FGSZ Ltd. will not run binding incremental capacity auctions for Interconnection point between Slovenia and Hungary in July 2021. As these incremental capacities are connected in the corridor Hungary-Slovenia-Italy the binding incremental capacity auctions in July 2021 on Slovenian-Italian Interconnection Point will not run either.
Nevertheless, in order to comply with the provisions set in the Article 26 of the CAM NC the non-binding incremental market demand assessment due in 2021, will be conducted according to the schedule provided in the CAM NC. All interested parties are invited to follow the publications on the website www.plinovodi.si via which the market participants will be informed on the details of the market demand assessment procedure in 2021.
Plinovodi d.o.o. has conducted a non-binding market demand survey on incremental capacity for interconnection points among Network Users between 5th July 2021 and 30th August 2021 according to the Articles 26-29 of the Commission Regulation (EU) 2017/459. Plinovodi d.o.o. together with adjacent TSOs publishes demand assessment report for interconnection points Murfeld/Ceršak, Gorizia/Šempeter, Rogatec and Tornyiszentmiklós/Pince.
Plinovodi d.o.o. has conducted a non-binding market demand survey on incremental capacity for interconnection points among System users between 5th July 2022 and 30th August 2022, according to the Articles 26-29 of the Commission Regulation (EU) 2017/459. Plinovodi d.o.o. publishes demand assessment report for interconnection points Murfeld/Ceršak, Gorizia/Šempeter, Rogatec and Tornyiszentmiklós/Pince.